Government's ReGen Exit Could Run Into 2027 With CI$17.3 Million Paid Out and No Settlement Agreed

Elgin Avenue's exit from the ReGen waste deal may now run into 2027.
Minister of Health, Environment and Sustainability Katherine Ebanks-Wilks MP told Parliament on 18 November that no final settlement has been agreed with the Dart-led consortium, that the Government has paid CI$17.3 million for works completed before the project was terminated, and that any further claims remain undetermined. "The Government remains determined to conclude the matter by 31 December 2026 or within Q1 of 2027," she said in a written answer to Parliamentary Question 63.
On 30 April, after the George Town landfill fire, she told the same House: "By the end of this year, we expect the ReGen exit to be concluded." The answer to Parliamentary Question 123, given the next day, said the Government was "committed to bringing them to an agreeable close by the end of this year". The minister has said the outcome of the exit talks is "critical" to how the Government moves forward with recycling and a long-term waste solution, and that without change the landfill will reach capacity by the end of 2030.
What ReGen was
ReGen was the name given to the Integrated Solid Waste Management System, a plan to replace the George Town landfill, known as Mount Trashmore, with a waste-to-energy plant and recycling facilities built and run by a consortium led by the Dart group. The consortium was chosen as preferred bidder in October 2017 and the Project Agreement was signed in March 2021, but financial close was never reached.
On 25 July 2024, Ms Ebanks-Wilks, then Minister for Sustainability and Climate Resiliency, announced that Cabinet had decided to begin discussions to exit the agreement. On 24 March 2025 the Government confirmed that the exit negotiation period "expired on Friday, February 28, 2025", that the project "has terminated with several residual issues remaining unresolved", and that it was "required to pay invoices totalling up to [CI]$17.7 million for work completed by the Dart Consortium and verified by the Government".
The question and the answer
Leader of the Opposition Joseph Hew MP, who represents George Town North, where the landfill sits, asked the minister for the current status of negotiations and whether a final settlement had been agreed, the total paid or payable in connection with the termination, and whether the Government remained on schedule to conclude by 31 December 2026.
To the first part the written answer was: "No. A final settlement has not yet been agreed."
On money, the minister said that "as of 28 February 2025 – the termination date, the Government had paid [CI]$17.3 million to the consortium for works completed and verified following termination". She added: "This sum is not for exit or termination but for works previously completed. These works included the end-of-life vehicle processing facility, and the end-of-life vehicle and metals processing works, which remain ongoing. Negotiations are still underway; therefore, any outstanding claims remain undetermined at this time."
On the timeline, she said the matter "remains dependent on the resolution of settlement of the exit negotiations and the need to ensure that the outcome represents the best interests for the Cayman Islands".
The answer does not give a figure for what the consortium is claiming, or say whether the Government expects to pay anything beyond the CI$17.3 million already paid.
A project that was terminated but not exited
The Government has said ReGen has ended and that the exit is unfinished. The Caymanian Journal (TCJ) reported in October that the ministry, in a letter of 3 September 2026 responding to a Freedom of Information request on the cost of ReGen, said "the project has not in fact been fully exited". Both the ministry and the Department of Environmental Health declined to answer TCJ's questions on the cost of ReGen, citing the Freedom of Information Act. The 18 November answer is the first public figure for what has been paid since the March 2025 release.
The exit also reaches beyond the Project Agreement. In her statement of 25 July 2024 the minister told the House that termination "does not affect Government's rights, obligations and liabilities under the land transfer agreement; and also, the early works agreements, which are separate from the project agreement". The 18 November answer does not address either.
TCJ's October report found that two Dart-affiliated companies continued to process end-of-life vehicles and scrap metal at the landfill after the declared termination, and the minister's answer describes those works as "ongoing".
Why the money was spent before the deal was done
The March 2025 release explained that the works being paid for "was carried out at the Consortium's cost and ahead of financial close, with the intent to reduce the length of the build programme for the new ISWMS project facilities". Cabinet, the minister said in July 2024, "was advised that in the event that the Government decided to exercise its right to terminate the project agreement, the parties will have no liability to each other except for any contractual liabilities accrued prior to termination of the project agreement".
The Office of the Auditor General, which reviewed the deal at the request of the incoming Government in 2021 and published a redacted version of its report on 24 January 2025, said the project would not provide value for money. Auditor General Sue Winspear said in the release accompanying that report: "The cost of ReGen increased significantly between the procurement and signing the Project Agreement. However, no updated value for money assessment was done."
The minister has relied on that finding to explain the exit. In April she told Parliament: "Based on a number of technical reports including a report by the OAG affirmed the view that the previous ReGen arrangement was considered as unaffordable, high risk and not delivering value for money. It would have committed this country to decades of financial obligation, leaving future generations in debt."
The Opposition's own record
Mr Hew's party signed the Project Agreement. The Progressives government led by Sir Alden McLaughlin signed the deal with the consortium in March 2021, weeks before that year's general election. When the exit was announced on 25 July 2024, Mr Hew, then Deputy Leader of the Opposition, challenged the weight the minister had placed on the absence of a signed power purchase agreement with Caribbean Utilities Company. "If you couldn't get them to sign a PPA now, how will you get them to sign in the next round?" he asked. Roy McTaggart, then Leader of the Opposition, told the House: "The project is dead. We accept that, but we have been trying for well over a year to get a figure from Government."
Mr Hew's 18 November written question asks only for the status, the cost and the date.
What is riding on the date
The minister's own account is that the long-term answer to the landfill waits on the exit. "As I mentioned at the beginning, the outcome of our exit negotiations is critical to how we move forward with the recycling workstream and the long-term solution," she said in the answer to Parliamentary Question 123 on 1 May.
In that answer and her statement the day before she set out a four-part plan: close the ReGen negotiations, improve landfill operations, reduce what goes into the landfill, and build a permanent solution. She allocated CI$6 million this year and CI$2 million next year to begin it. She said a steering committee would be in place by summer and that the Outline Business Case for the permanent solution, defining the preferred option, its cost, land requirements and environmental performance, was expected "by the fall of 2027".
"If we keep sending the same volume of waste to the same place, the current landfill will reach capacity by the end of 2030," she told the House on 30 April. A new lined landfill on Government land next to the current tipping area, known as Site 4, would extend that to 2036, she said, "provided there are no major hurricanes".
For the people near the dump
The minister opened her 30 April statement by addressing "those who woke up to smoke in the air, who kept their children home from school, who sat in traffic because roads were closed, who worried about what they were breathing". Mr Hew told the House in July 2024 that the smell reached from West Bay Road "all the way down to the area at Pizza Hut", depending on the wind. For them, the practical questions are what the exit will finally cost, when the site next to their homes stops growing, and when the permanent plant will be built. The 18 November answer settles none of the three, and moves the first date the Government had given itself for the exit by up to three months.
What happens next
The Government's stated timetable is a concluded exit by 31 December 2026 or by the end of March 2027, a steering committee for the permanent solution already due, and an Outline Business Case by late 2027. The amount the consortium is claiming, the terms on which the Government might settle, and the position under the land transfer and early works agreements have not been published. Parliament's next opportunity to ask is at its next sitting; the minister's written answer says the Government "remains determined" to finish.